Hello Experts,
I need your inputs on the below issue.
Process chain runs every day at 4:00 IST(Average run time is 20 min).
Process chain flow:
IP àDTP(DSO)à Activation à DTP (DSO) à Activation à OHD(Open Hub)
And yesterday around 5:52 IST DTP marked in red above started automatically and all the sub-sequent steps also completed and open hub sent 2 files which is not supposed to be.
- I could see process chain logs for yesteray only once at 4.00 IST
- Info package has only ran for yesterday at 4.00 IST and hardly it has run for 1 min there is no chance that it ran for long time and back up job started and later it got completed.
- This DTP is part of only this chain and not part of any other chain
I have checked SCN and couldn’t find related posts. Could any one explain/help me what caused to start the DTP here and also suggest me how to search OSS notes exactly for this.
Your immediate answer is helpful/appreciated.
Thanks in advance!
Regards,
Prakash